Work Package · WP0

Inception and compliant procurement

Cross-cutting · runs before WP1–WP5

Back to work packages →

Scope

A short inception phase opens the project: shared technical specifications for hardware, software and data flows are finalised, a data protection and cybersecurity baseline is set for the DIK/EWS, and all procurement is front-loaded under the project's VAT and import-duty exemptions.

Activities

  1. —Finalise shared technical specifications for hardware, software and data flows.
  2. —Complete a data protection impact assessment (DPIA) and minimum cybersecurity controls for the DIK/EWS.
  3. —Front-load all procurement under the project's VAT and import-duty exemptions.
  4. —Joint kick-off with cooperatives and public agencies to confirm field access, data sharing and roles.

Rationale

Completing procurement and technical specifications at the start aims to reduce the risk of schedule delays, ensure that systems are interoperable from the outset and create a documented compliance record.